n6.MAINTENANCE AND PERMITS
n
nCustomer shall (a) maintain the
generator and interconnection facilities in a safe and prudent manner and in conformance
with all applicable laws and regulations including, but not limited to
Section 5, and (b) obtain any governmental authorizations and permits required for the
construction and operation of the generator and interconnection facilities.
Customer shall reimburse MPC for any and all losses, damages, claims, penalties, or
liability it incurs as a result of Customer’s failure to obtain or maintain any
governmental authorizations and permits required for construction and
operation of Customer Facility.
n
7.ACCESS TO
PREMISES
n
nMPC may enter Customer’s premises
(a) to inspect, at reasonable hours, Customer’s protective
devices and read or test meters, and (b) to disconnect, without
notice, the interconnection facilities if, in MPC’s opinion, a
hazardous condition exists and such immediate action is necessary to
protect persons, or MPC’s facilities, or property of others from
damage or interference caused by Customer’s renewable
source energy generation facilities, or lack of properly operating
protective devices.